All
temporarily positioned equipment removed to permit placement
of air handling units.

With
the installation of new air handling unit 3 under the chancel,
the east and west air supply tunnels running from the south
cross tunnel have been closed at the north end of the sanctuary.
This is a view of the east tunnel.

View
of wall in west tunnel.

Installation
of gas humidifier in boiler room.

Four
of our air handling components still on the truck that delivered
them.

Loading
of the component parts for air handling unit 3 (which will
be located under the chancel) onto a local truck to take them
to the front entrance of the church for easier entry into
the chancel area.

Bringing
the air handling unit 3 components off of the local truck
into the construction doors for the sanctuary.

Off-loading
the air handling unit 1 and air handling unit 2 components,
which will be located in the mechanical equipment room in
the basement
.

Staging the first piece.

Lifting
the second piece.

Little
ducks all in a row.

Moving
the first piece of the chancel unit from the sanctuary floor
to the chancel floor level.

"It
worked, didn't it."

At
the same time, the carpenters are measuring for the installation
of the 4-piece molding on the cove.

"Plan
B" for moving the air handling unit 3 components from
the sanctuary to the chancel.

Cutting
of the first of the molding trim pieces .

The
finished "floor box" that was poured March 5.

Installing
the first trim piece of molding; this is the base into which
the flat sheet will be placed.

The
completed first piece of molding.

Installation
of the first component piece of molding in the adjacent bay.

|