During
the tenth week of our sanctuary
renovation project, we did the following:
- Painted
organ chambers.
- SPL
installation continued, installed "rack room"
racks.
- Received
and stained wood molding and trim pieces for color test.
- Stained
and installed finished wood molding and trim pieces.
- All
three new air handling units arrived; one full day to bring
them into the building .
- Installed
air handling unit 3 under the chancel.
- Installed
limestone steps up to the chancel after installation of
air handling unit 3 under the chancel.
- Continued
mechanical and electrical installations for air handling
units 1 and 2 in the mechanical equipment room.
Photos:
|