Initial
pressure check on chilled water supply for air handlers.

Insulating
the air ducts in the narthex; ceiling supports completed.

Audio
leads through floor to back of north rack room rack in media
center.

Electrical
power leads through floor on west wall of rack room.

South
wall rack frame.

First
day's completed stained molding panels.

Installing
recessed light in chancel ceiling.

Insulated
air ducts to east side of balcony.

"Musical
Chairs" FUMC-B style: samples for new choir chairs.

More
chairs.

Starting
to stain 3 molding trim pieces.

4-inch
"Full Flow" ball valve close-up - fully open. We
have many of these in our water systems for both heating and
cooling.

Installation
of new electrical panel in rummage sale storage room that
will supply power to Air Handler 1 for the sanctuary. Air
Handler 2 for Fellowship hall will be supplied by an existing
run from the panel in the boiler room used previously.

Water
runs from the chiller after insulating.

Panel
end of electrical power run from main transformer in south
tunnel to new panel in rummage sale storage room.

Main
panel end of the same electrical power run.

PROGRESS!
The first load of scaffolding from the balcony being taken
away.

Pulling
wires through previously installed conduit.

Heating
and cooling duct being installed under the chancel and altar.

Completed
stained molding trim pieces.

Frank
Schmidt signing for delivery of one of the speaker clusters.

Starting
to set the circulating pumps for Air Handlers 1 & 2.

Added
insulation of all pipe joints in addition to the pipe runs
themselves.

Further
progress on circulating pump installation; note ball valves
in each run.

Attaching
the first piece of "blue board" to the narthex ceiling
prior to beginning plastering of the ceiling.

No
sooner do we get them up than we cut holes in them for lights
and speakers.

Kevin
attaching a ball valve to a nipple before installing on the
pipe run.

The
"blue board" installation proceeding apace.

Duct
work coming through the wall from under the chancel into the
west organ blower pit ...

...
and then up the wall into the west organ chamber above.


Gas-fired
humidifier being readied for installation in the boiler room.

Initial
setting of circulating pumps completed.

Air
duct through floor in northwest corner of chancel - actually
the crawl space under the altar which is separated by a wall
from the chancel - that will terminate in the organ chamber
on that side of the altar.

Duct
work in the west end and against the north wall of the crawl
space under the altar.

|