During the seventh week of our sanctuary renovation project, we did the following:

  • Installed and patched balcony ceiling.
  • Installed new recessed light fixtures in narthex.
  • Painted balcony ceiling.
  • Patched sanctuary ceiling.
  • Constructed ceilings and floors and drywall the walls of the new "upper" organ chambers above the existing east and west organ chambers.
  • Constructed new block walls at the point that the south cross tunnel under the narthex encounters the "inside walls" of the east and west sanctuary air supply tunnels. New air supply ducts will pass through and end at the "outside" edge of these walls.
  • Installed hanger brackets and upper track for folding wall between sanctuary and narthex.

Photos:



The Cross and Flame is a registered trademark of The United Methodist Church.®
Copyright 1998-2008. First United Methodist Church.
1589 West Maple Road, Birmingham, Michigan 48009 U.S.A.
248-646-1200.

Map and Contact Information

Contact Us | Calendar of Events | Sermon Archive | Announcements | Steeple Notes (newsletter) | Mission and Outreach | Music | Prayer and Healing | Christian Education | Christian Life Center | Adults | Youth | Children and Families | About Us | Virtual Bookstore | Online Donations | Monday Memo |