|
During
the sixth week of our sanctuary
renovation project, we did the following:
- Installed
new trusses and steel decking for the chancel floor
- Poured
the new chancel floor
- Built
new light coves (raceway) along each side of the sanctuary
at the juncture of the side wall and the ceiling, replacing
the existing molding which was removed earlier
- Began
installation of new air handling systems duct work and controls
- Erected
scaffolding and installed drywall on the balcony ceiling
- Constructed
ceilings and floors for the new "secondary chambers"
above the existing chambers in both the east and west organ
chambers
- Did
ongoing electrical, mechanical, and carpentry work
Installation
of "C" sections to support trusses and decking.

Installing
trusses and steel decking for the chancel floor.




Frank
Schmidt, site superintendent from the George Auch Company,
our construction management company. "X" marks the
spot for
the new west side chancel door, replacing the one that has
been blocked up.


"Tacking"
the steel decking to the trusses.

Chancel
floor mounted frame and trap door for access to the chancel
crawl space after pouring the concrete floor

Trap
door frame installed before pouring the concrete.

Installing
drywall on the balcony ceiling.
Last
bay of the balcony above the antiphonal organ after
removal of old acoustical ceiling tile and before
installation of new drywall.

Installation
of steel brackets to holdthe molding covering
the raceway/cove that will hold sound and lighting fixtures.

Installing
balcony scaffolding for electrical, sound and paint work.

Building
new light coves.


Work
going on in the adjacent media center.

Enclosing
the media center alcove to create the "rack room"
for the electronic acoustics controls

Center
"return air" tunnel under Sanctuary;
right side conduit runs for audio;
left side runs for electrical power.

From
center to east side of the south cross tunnel under
the narthex; large conduit is the main power feed to
the sanctuary from the transformer.

View
east to west inside the south cross tunnel with the entrance
to the center tunnel (the return air tunnel) on the right.

Blocking
up the existing south chancel door
on the east side of the chancel.

Added
securing with screws of existing ceiling drywall panels and
"spackling" of existing nail and new screw "pops"
(heads).

Balcony
scaffolding pieces being brought in to the sanctuary.
Horizontal platform pieces at the left.

Preparation
for installation of the air handling unit
in mechanical equipment room.

Electrical
runs through new access hole in back corner of narthex.

|