Sanctuary Renovations and Organ Replacement: Photos January 24-28, 2005

During the fifth week of our sanctuary renovation project, we did the following:

  • Poured the new cement floor for the crawl space (plenum) under the chancel
  • Poured the air handling equipment mounting pads
  • Removed the air conditioning systems on either side of the balcony
  • Installed the new floor drain in the mechanical equipment room
  • Cut and cored passageways for the HVAC supply to the balcony and narthex
  • Installed duct work for the #3 air handling system under the chancel while the chancel was open

Pouring the cement floor for the crawl space under the chancel.


The new floor drain in the mechanical equipment room.


Newly cored passageway for the HVAC supply to the narthex.


Cutting a channel to "flush mount" light and
sound controls in the west side narthex column.