During
the fourth week of our sanctuary
renovation project, we demolished the chancel floor,
removed the wall between the sanctuary and the narthex,
removed the ceiling tiles, began installing mechanical and
electrical equipment, completed removing the framing around
the organ chambers and also the old blower and bellows,
removed wall moldings, and formed pads for mounting the
new air handling equipment.
We
demolished the chancel floor.











We
removed the wall between the sanctuary and the narthex.

We
removed the ceiling tile.



We
removed the framing around the organ chambers.

We
began installing electrical equipment.