Sanctuary Renovations and Organ Replacement: Photos January 17-21, 2005

During the fourth week of our sanctuary renovation project, we demolished the chancel floor, removed the wall between the sanctuary and the narthex, removed the ceiling tiles, began installing mechanical and electrical equipment, completed removing the framing around the organ chambers and also the old blower and bellows, removed wall moldings, and formed pads for mounting the new air handling equipment.


We demolished the chancel floor.


We removed the wall between the sanctuary and the narthex.


We removed the ceiling tile.


We removed the framing around the organ chambers.


We began installing electrical equipment.