During the third week of our sanctuary renovation project, we completed removing the existing organ, removed existing mechanical equipment, prepared for demolition of the chancel floor, and began removing the east chancel hallway circuit breaker cabinets.


We completed removing the organ, then loaded it
onto a truck to ship it to its new home in Memphis.

Our organist Doris Hall with pipes from the existing organ.



We began removing the circuit breaker cabinets
from the east chancel hallway.


We removed the glass from the windows in the wall between the narthex and the sanctuary in preparation for replacing that solid wall with a folding wall which will incorporate the same glass windows.


We continued to remove other things from the sanctuary in preparation for the reconstruction work.